Miri gets RM255.8 mln road upgrades, including four-lane route to Brunei border

Nanta speaking to reporters at the event on Nov 29, 2026. Photo credit: Ukas
Advertisement

By DayakDaily Team

KUCHING, Nov 29: Two road projects worth a combined RM255.8 million have begun in Miri, including a four-lane upgrade of the Kuala Baram–Sungai Tujuh route and improvements to nine locations along the Pan Borneo Highway Redline.

According to a report by the Sarawak Public Communication Unit (Ukas), the projects were launched through a groundbreaking ceremony officiated by Works Minister Datuk Seri Alexander Nanta Linggi at the project site today.

Advertisement

Worth RM136.1 million, the Trans Borneo Highway (LTB) Miri Section involves upgrading the 4.95km route from the Kuala Baram junction to the Sungai Tujuh Immigration, Customs, Quarantine and Security (ICQS) Complex from a two-lane single carriageway to a four-lane dual carriageway.

The scope also includes rebuilding the roundabout before the Sungai Tujuh ICQS Complex to increase road capacity and improve traffic flow towards the Brunei Darussalam border.

Meanwhile, a separate RM119.7 million project will upgrade 17.1km of the Sarawak Pan Borneo Highway Redline across nine strategic locations.

Works include road resurfacing through milling, Cold In-Place Recycling (CIPR) and new asphalt layers, alongside improvements to road shoulders, dividers, drainage systems, signage and road markings.

Motorists travelling along the Tudan route and surrounding areas are expected to benefit from smoother journeys, improved road safety and greater driving comfort.

Speaking on the wider Trans Borneo Highway development, Nanta said the 93.25km project covers three main sections in Miri, Limbang and Lawas to strengthen transport connectivity in northern Sarawak and facilitate cross-border travel.

The Miri Section is scheduled for completion in October 2029 after three years of implementation, while the Redline upgrading works are expected to take 16 months and finish on Jan 16, 2028.

Separately, the 786km Sarawak Pan Borneo Highway from Telok Melano to Miri has reached 99.98 per cent completion, with 10 of its 11 work packages fully open to motorists.

Also present at the ceremony were Sarawak Transport Minister Datuk Seri Lee Kim Shin and Deputy Foreign Minister-cum-Sibuti MP Datuk Lukanisman Awang. —DayakDaily