By DayakDaily Team
PADAWAN, Nov 29: A new Type 5 health clinic in Tebedu is expected to take 26 months to complete, offering a long-term solution to the deteriorating condition of the existing facility.
According to a TVS report, Gabungan Parti Sarawak (GPS) candidate for the Tebedu seat, Simon Sinang Bada, said the project had been approved and was currently undergoing the procurement process before construction could begin.
He said the construction site near a church in Tebedu had been identified and handed over to the relevant authorities, with the Serian Divisional Public Works Department (JKR) responsible for managing the project’s implementation.
“This is certainly good news as the condition of the existing clinic has become quite dilapidated.
“I hope construction work can begin soon under the Ministry of Health (MOH), as the construction site has already been handed over to the relevant authorities,” he said when speaking to reporters during the launch of the GPS Sarawak Election 2026 campaign machinery for Zone 4 at Dewan Kampung Sinjok Siburan today.
The proposed development will comprise a health clinic block, an X-ray block, eight units of Class G apartment quarters, and double-storey semi-detached Class D quarters.
It will also include supporting facilities such as an ambulance garage, store, pump house, and guardhouse, alongside piling works, mechanical and electrical installations, and external works.
Simon said an allocation of RM300,000 had previously been channelled in 2022 to improve the existing clinic’s facilities and infrastructure.
Among the improvements were relocating examination rooms to the ground floor to make access easier for patients, particularly senior citizens and wheelchair users who previously had to use the stairs.
Air-conditioning was also installed in the examination rooms and pharmacy, while additional seating was provided in the waiting area to improve patients’ comfort.
“These were among the facilities provided as short-term measures to address the problems. However, the long-term solution is the construction of a new health clinic,” he said.
Simon added that the old clinic building would eventually be handed over to the MOH to determine its future use, including the possibility of converting it into a Divisional Health Office (PKB) or community centre. — DayakDaily