By DayakDaily Team
LAWAS, Nov 27: A total of RM57 million has been allocated for the development of the Banting Resettlement Scheme (SPS), which will provide 45 units of affordable Sapphire 1 homes on a site spanning approximately 15 hectares.
In a TVS report, Land Custody and Development Authority (LCDA) general manager Datu Zaidi Mahdi said the project would be implemented under the 13th Malaysia Plan (13MP).
He said the project would involve not only house construction but also the development of basic infrastructure to ensure the resettlement area is equipped with the necessary facilities for residents.
“LCDA’s task here is very different from the Trusan Village Expansion Scheme (SPK), which was developed on a site that already has infrastructure.
“For the SPS here, we have to start from scratch, including site clearing, land filling and infrastructure development before the houses can be built,” he said at the symbolic groundbreaking ceremony for the Banting Resettlement Scheme here today.
On the project timeline, Zaidi said it was expected to take 36 months to complete due to its scope of work, which includes site preparation, infrastructure development, and subsequent house construction.
The double-storey affordable homes, each measuring 870 square feet, will feature three bedrooms, two bathrooms, a living room, kitchen and dining area, as well as a 1,200-litre water storage tank. — DayakDaily