RM285 mln Batang Igan Bridge hits 82 pct completion, on track for Dec 2025 finish

Uggah addresses the media on the progress of the RM285 million Batang Igan Bridge project in Mukah on April 23, 2025. Photo: TVS
Advertisement

By DayakDaily Team

KUCHING, April 23: The RM285 million Batang Igan Bridge project has reached 82 per cent completion and is progressing smoothly toward full completion by December 2025, according to Sarawak Deputy Premier Datuk Amar Douglas Uggah Embas.

Uggah, who visited the construction site today, expressed satisfaction with the project’s progress and the performance of the contractor, according to a TVS news report.

Advertisement

“We are very pleased that the Batang Igan Bridge project has achieved 82 per cent completion, with only 18 per cent remaining,” he told reporters during the site visit in Mukah.

He stressed the importance of maintaining steady construction progress to ensure timely delivery in line with the State’s development timeline.

“We’ve informed the contractor that they must achieve at least three per cent progress every month. With this target and schedule, we are confident the project will be completed on time,” Uggah added.

He also highlighted the role of frequent monitoring visits in preventing potential delays.

“We actively turun padang (go to the ground) to ensure all our projects are on schedule. It allows us to detect issues early before they become major obstacles,” he said.

The 1.4-kilometre bridge across Batang Igan is expected to significantly enhance rural connectivity and accessibility once completed.

So far, the project has encountered minimal issues and continues to progress as planned. — DayakDaily