JKR: Sg Tutoh Bridge in Baram reaches 91.58 pct completion, ahead of schedule

JKR reports Sungai Tutoh Bridge in Baram is now at 91.58 per cent completion. Photo credit: JKR

By DayakDaily Team

KUCHING, March 26: The Sarawak Public Works Department (JKR) has revealed that the construction of the 104m Bailey bridge for Sungai Tutoh in Baram, Miri is currently at 91.58 per cent completion progress.

According to a video posted on its Facebook page, the ‘Sungai Tutoh Bridge, Baram, Miri’ project will benefit over 10,000 people from Long Lama to Limbang and Lawas because the bridge is the main connection to Limbang-Lawas without crossing the Brunei border.


JKR additionally stated that the 91.58 percent completion progress is 69 days ahead of the scheduled completion date. — DayakDaily