By DayakDaily Team
DALAT, Nov 21: Long-standing complaints over narrow, uneven roads in Oya-Dalat are set to be addressed through a RM204.75 million upgrading project covering 18.2 kilometres, bringing improvements to road safety, accessibility and driving conditions for local residents.
As reported by TVS, Sarawak Minister of Women, Childhood and Community Wellbeing Development Dato Sri Fatimah Abdullah said the project covers two stretches, namely 15.7 said the project involves upgrading 15.72 kilometres of Jalan Oya-Dalat and another three kilometres of Jalan Oya Bypass.
She said both roads would be upgraded from R2 to R3 standards, with wider road surfaces, road shoulders, two roundabouts and improved drainage systems.
“This is an effort that we are implementing in stages. Alhamdulillah, the allocation has been secured, and the next processes involve surveys, design and project implementation.
“We want these roads to be upgraded to the wider R3 standard, complete with road shoulders,” she said speaking at the 2026 Dalat District Melanau Traditional Food Carnival at the Dalat Riverfront here today.
Explaining the factors behind the deteriorating road conditions, Fatimah said the swampy terrain in the area contributed to road subsidence, while frequent use by heavy vehicles transporting sand and oil palm produce added to the strain.
She added that the routes also supported the movement of lorries serving various development projects, including the construction of village roads, mosques and other infrastructure.
Meanwhile, Fatimah said the government had already approved street lighting projects for Oya and Dalat under the Rajang Delta Development Agency (RADDA), dismissing social media claims that the issue had been neglected.
She said the installation of 88 streetlights along Jalan Oya-Dalat, involving an allocation of RM380,000, was almost complete and had undergone testing on Nov 19.
The Senau street lighting package, involving 41 poles at a cost of RM168,000, is scheduled for completion in December 2026.
Another package covering the Dalat-Kekang and Dalat-Medong routes will involve the installation of 399 streetlights at a cost of RM1,494,336.78.
Installation works are expected to begin in December, with completion targeted for the first quarter of 2027.
Fatimah said the infrastructure improvements reflected the State government’s continued commitment to ensuring that development benefits reached communities across Sarawak, including those in rural areas. — DayakDaily