JKR implements 99 federal projects worth RM12b to support S’wak’s devt, 35 now underway

Nanta (centre) witnesses the symbolic handover of the completed Armed Forces Family Housing project at Kem Muara Tuang on Nov 16, 2026.
Advertisement

By Amanda L

KUCHING, Nov 16: A total of 35 federal development projects worth RM5 billion are currently being built in Sarawak, out of a wider portfolio of 99 projects valued at RM12 billion under the Public Works Department (JKR) Malaysia.

Works Minister Datuk Seri Alexander Nanta Linggi said the remaining projects were at various stages of implementation, while those worth RM50 million and below had been handed over to JKR Sarawak.

Advertisement

“Of these, 35 projects worth RM5 billion are currently under construction.

“Projects worth RM50 million and below have been handed over to JKR Sarawak for implementation, while the RM12 billion covers projects managed by JKR Malaysia at the federal level,” he told reporters after attending the handover ceremony for the completed Armed Forces Family Housing (Rumah Keluarga Angkatan Tentera, RKAT) project at Kem Muara Tuang today.

On project delivery, Nanta stressed that contractors must take full responsibility for delays caused by weaknesses within their own operations, including poor management, financial constraints and insufficient manpower.

“Where they are responsible, they must be responsible entirely.

“We do not want projects to be delayed because of them, due to weaknesses in their management, financial constraints or their inability to manage workers on site.

“There are many large projects where the number of workers available is insufficient. That is the contractor’s responsibility,” he said.

However, he said delays could also result from factors beyond contractors’ control, such as land acquisition, utility relocation, detailed land surveys and changes in project scope.

On whether contractors who completed projects ahead of schedule would receive incentives, Nanta said the Works Ministry did not have a formal arrangement to offer bonuses or additional projects as rewards.

Nevertheless, he said JKR Malaysia kept records of contractors’ performance and reliability when assessing their ability to deliver government projects.

“We know from our records which contractors we can categorise as reliable and trust to deliver quality work. There are contractors who perform less satisfactorily, while others are not reliable at all,” he said.

Nanta said the ministry had also held brainstorming sessions and retreats over the past year to review weaknesses in project implementation and strengthen preparations for projects scheduled in 2027.

He said the discussions, involving the ministry’s Secretary-General, Deputy Minister and division secretaries, focused on improving the implementation of projects under the ministry’s allocation.

Addressing technical capacity, Nanta said shortages of technical personnel, particularly engineers and land surveyors, had previously been identified as among the factors affecting project implementation in Sarawak and Sabah.

Following an improvement exercise involving JKR Malaysia, JKR Sarawak and JKR Sabah in Sarawak in early 2025, he said Sarawak had recruited several hundred additional technical personnel to address the shortage.

A similar exercise was subsequently held in Sabah in July this year to identify weaknesses and strengthen its technical capacity.

The minister said improving project implementation and addressing technical manpower shortages were essential to ensuring that federal development projects in Sarawak and across the country were delivered effectively. — DayakDaily