DARO, Nov 10: Construction of the Daro District Public Library has entered its final phase, with physical progress at 90.6 per cent, including lift installation.
The project, which will also house a Digital and Innovation Centre, is expected to be fully completed by January next year.
The update was shared by Daro incumbent Dr Safiee Ahmad through his official Facebook page today.
He said the new library would provide residents with more comfortable, conducive facilities for learning, reading, and reference purposes.
“The facility will particularly benefit young people, while also promoting a reading culture and lifelong learning.
“It will also serve as an important infrastructure facility in efforts to strengthen human capital development in the district,” he said.
He said cooperation and coordination among all parties must continue to ensure that any issues arising during the project’s implementation could be addressed promptly.
He added that continuous monitoring was also important to ensure the project was completed on schedule and delivered its full benefits to the people. — DayakDaily