By DayakDaily Team
KUCHING, Nov 18: A total of RM717.27 million has been allocated for 27 water supply projects in Limbang Division, of which 22, or 81.5 per cent, have been completed.
In addition, RM80.8 million has been set aside for 14 projects to replace 119.8 kilometres of old and dilapidated water pipelines across the division, with the works being carried out in phases and expected to be completed by 2029.
According to a report by the Sarawak Public Communications Unit (Ukas), the projects are aimed at strengthening water supply infrastructure and improving residents’ access to clean and treated water.
Sarawak Minister for Utility and Telecommunication Dato Sri Julaihi Narawi said the RM717.27 million allocation covered the implementation of all 27 water supply projects in the division.
“For the Limbang Division, RM717.27 million has been allocated for the implementation of 27 projects, with 22 projects or 81.5 per cent already completed,” he said at the groundbreaking ceremony for the Pengalih Lakutan Water Treatment Plant in Lawas yesterday (Nov 17).
Currently, Limbang District has a water supply coverage of 75 per cent, compared to Sarawak’s overall coverage of 86.1 per cent.
Among the major completed projects is the upgrading of the Berawan Water Treatment Plant in Limbang, which doubled its production capacity from 20 million litres per day (MLD) to 40 MLD.
Meanwhile, Julaihi said the pipeline replacement works in Limbang were part of Sarawak’s wider 2,740-kilometre Old and Dilapidated Water Pipe Replacement Programme, valued at RM1.1 billion.
The programme aims to improve water distribution system efficiency and reduce non-revenue water (NRW) losses across the State.
He further said the Sarawak Government was developing the Sarawak Water Supply Grid System, which involves 32 main water treatment plants and a 2,934-kilometre pipeline network to ensure long-term water supply across the State.
Also present during the event was Deputy Premier Datuk Amar Awang Tengah Ali Hasan. – DayakDaily