KUCHING, Nov 18: A total of 125 federal development projects and maintenance works worth RM12.38 billion are underway in Sarawak, with another 18 projects worth RM1.14 billion planned for 2027.
These developments were discussed during the Ministry of Works’ Customer Ministry Infrastructure Development Project Monitoring Meeting No. 4/2026, chaired by Deputy Works Minister Datuk Seri Dr Ahmad Maslan at the State Legislative Assembly (DUS) building here, today.
According to the Ministry of Works (KKR), the ongoing portfolio comprises 99 physical development projects worth RM12.17 billion and 26 maintenance, rehabilitation, renovation and upgrading works worth RM206.27 million.
Of the 99 physical development projects, three are preliminary works, 36 are in the pre-construction phase, 35 are in the construction phase, while 25 have been completed and are under the Defects Liability Period (DLP).
One of the 35 projects in the construction phase has since been completed, leaving 34 still under implementation as of Nov 18.
Looking ahead, the federal government has planned another 18 development projects in Sarawak under the 13th Malaysia Plan (RMK13) Rolling Plan 2 (RP2) for 2027, with an estimated total cost of RM1.14 billion.
The bulk of these projects will be under the Ministry of Education Malaysia, which accounts for 14 projects, followed by two under the Ministry of Health Malaysia. The Ministry of Defence and Ministry of Home Affairs will each have one project.
The projects cover the development of education, healthcare and security facilities, aimed at strengthening basic infrastructure and improving public access to services.
Beyond the new projects planned for next year, another 36 projects worth RM5.61 billion remain in the pre-construction phase.
KKR said efforts were being focused on ensuring the necessary planning, design, approvals, procurement and site preparations were completed in an orderly manner before construction could begin.
On the implementation front, four projects in Sarawak remain categorised as sick as of Nov 18, after one of the five previously identified projects was successfully completed.
The situation in Sarawak comes amid an overall improvement in the implementation of federal projects nationwide, with the number of sick projects under the supervision of the Public Works Department (JKR) Malaysia falling from 38 in October to 26 as of Nov 16.
An analysis of the 26 remaining sick projects found that contractor performance accounted for 81 per cent of the recorded causes of delays, while the remaining 19 per cent involved other factors.
Among the contractor-related problems were poor workforce management (19 per cent), weak internal contractor management (18 per cent), ineffective work planning and scheduling (15 per cent), contractors’ cash-flow problems (12 per cent) and poor construction material management (eight per cent).
Other factors included technical issues, shortages and rising prices of construction materials and fuel, delays in utility relocation, local authority approvals and access constraints at construction sites.
To address these problems, KKR, through JKR Malaysia, is continuing regular monitoring of physical progress, implementing recovery plans, assessing contractors’ capabilities and coordinating with client ministries and relevant agencies to resolve implementation issues.
The ministry also warned that contractual action would be taken against underperforming contractors. These measures include recovery plans, the imposition of Liquidated and Ascertained Damages (LAD) and possible contract termination for projects deemed no longer viable for recovery. — DayakDaily