KUCHING, Nov 18: The Ministry of Works has taken a firm stance against the issue of delays in rural educational building infrastructure in Sarawak by imposing fines and contract termination notices on contractors of four school projects categorised as delayed (sick) projects.
Deputy Minister of Works Datuk Seri Ahmad Maslan stated that the four school projects involve Sekolah Menengah Kebangsaan (SMK) Tinjar in Baram, Sekolah Kebangsaan (SK) Sebat in Lundu, SMK Belaga, and SK Abang Leman in Saratok, each experiencing project delays of between 18 and 33 per cent.
“For example, at SK Abang Leman – which involves the construction of classrooms, a full replacement of 30 classrooms, a hostel for 600 students, and 12 units of teachers’ quarters – we issued a notice for contract termination to the contractor on November 10.
“For SMK Belaga, SK Sebat, and SMK Tinjar, the contractors have been imposed with LAD (Liquidated and Ascertained Damages), which are fines. That is our action,” he said.
He said this during a press conference after conducting a site visit and attending the 4th Series 2026 People’s Infrastructure Construction Project Monitoring Meeting of the Client Ministry at the State Legislative Assembly Building here today.
Regarding the progress of projects nationwide, Ahmad stated that out of a total of 880 projects worth RM51.75 billion currently in the construction phase under the monitoring of the Public Works Department (JKR), 272 projects are ahead of schedule and 311 projects are on schedule.
According to him, continuous monitoring and intervention measures implemented have shown positive developments, with the number of sick projects at the national level successfully reduced to 26 projects, or 2.97 percent, compared to 38 projects previously.
Meanwhile, he stated that a total of 18 development projects in Sarawak have been listed under the Second Rolling Plan (RP2) of the Thirteenth Malaysia Plan (RMK-13) for 2027, with an estimated total cost of RM1.14 billion.
“Out of these 18 projects, 14 involve the Ministry of Education, two projects are under the Ministry of Health, one project is under the Ministry of Defence, and one project is under the Ministry of Home Affairs,” he said. – Bernama