Batang Lupar Bridge 2 reaches 68 pct completion, set to open by March 2026

Cassidy (centre) during a visit to the Batang Lupar Bridge No. 2 project site in Betong on Oct 21, 2025. Photo credit: JKR Sarawak
Advertisement

By DayakDaily Team

BETONG, Oct 22: The construction of Batang Lupar Bridge No. 2, from Sri Aman to Betong Interchange, as part of the Sarawak Second Trunk Road Package B4, has achieved a physical progress of 68.43 per cent and is expected to open to the public in March 2026.

Public Works Department (JKR) Sarawak director Datu Ir Dr Cassidy Morris conducted an official site visit to the project on Tuesday (Oct 21).

Advertisement

In a post shared on its social media, JKR Sarawak highlighted that the project, part of the broader Sarawak Second Trunk Road initiative, aims to strengthen the State’s primary road network, accelerate socio-economic development in rural areas, and enhance connectivity between the central and western regions of Sarawak.

Progress of the construction of the Sarawak Second Trunk Road Package B4 – Batang Lupar Bridge No. 2 from Sri Aman to Betong Interchange as of Oct 21, 2025. Photo credit: JKR Sarawak

During the visit, he also inspected the Jelukong Rest and Service (R&R) area and a bus stop along the Pan Borneo Highway.

He urged road users to make proper use of public facilities and avoid littering at bus stops, emphasising the importance of maintaining cleanliness and upholding the image of the State’s public infrastructure.

The Sarawak Second Trunk Road is seen as a major development effort to support economic growth and improve accessibility across the State, particularly benefiting rural communities along the route. — DayakDaily