Batang Lupar 1 Bridge eyes early launch by May 15, 2026

Uggah during his visit to the Batang Lupar 1 Bridge project site in Sebuyau on Oct 5, 2025. Photo: UKAS
Advertisement

By DayakDaily Team

KUCHING, Oct 5: Construction of the Batang Lupar 1 Bridge in Sebuyau is moving ahead smoothly, with hopes of opening ahead of schedule by May next year as it is now at 87 per cent completion.

According to the Sarawak Public Communication Unit (UKAS), Deputy Premier Datuk Amar Douglas Uggah Embas said that construction works are progressing smoothly following a few technical issues that were solved.

Advertisement

“Today, the contractor announced a ‘milestone’, in which that on Jan 15 next year, the bridge connection works will be carried out, and by May 15, we hope to open the bridge ahead of schedule.

“This is a very positive development. They are carrying out their duties excellently, and we are confident in the contractor’s capabilities. The weather has also been favourable, so we believe the construction schedule can be achieved as planned,” he told the media after inspecting the project site today.

Uggah added that the Sarawak Public Works Department (JKR) will continue to closely monitor the project’s progress to ensure any issues that arise can be addressed promptly, so that construction stays on track.

Meanwhile, he also reported that the Sebuyau–Lingga Highway construction project is currently 76 per cent complete.

The Batang Lupar Bridge Project, with a cost of RM848.7 million, is one of Sarawak’s iconic infrastructure projects. It will connect Sebuyau and Triso, and is set to become a new landmark for the State’s development.

Previously, it was reported that the bridge is expected to be completed by mid-2026. — DayakDaily